AMBER Archive (2009)

Subject: Re: [AMBER] skip parallel test

From: David A. Case (case_at_biomaps.rutgers.edu)
Date: Tue May 05 2009 - 10:34:14 CDT


On Tue, May 05, 2009, Collins Nganou wrote:
>
> I would like to know if it is possible to skip parellel test in amber 10?

Certainly! Running "make test" just tests the serial code. You might also
want to run "make test.serial.QMMM" if you plan to use QMMM. See the top of
$AMBERHOME/test/Makefile for targets that are available.

>
> If yes, how can I do it and what could be the consequences ?

If you don't plan to run parallel jobs, there is not point in running the
parallel tests. But if you do plan to run parallel jobs, you should make sure
the test cases work.

...dac

_______________________________________________
AMBER mailing list
AMBER_at_ambermd.org
http://lists.ambermd.org/mailman/listinfo/amber